10 COMMISSIONING
10.1 PRE-COMMISSIONING
Before the system is started, it is recommended that the following checks are made:-
The unit is adequately cooled and all the wiring to the module is of a standard and rating
compatible with the system. Check all mechanical parts are fitted correctly and that all electrical
connections (including earths) are sound.
The unit DC supply is fused and connected to the battery and that it is of the correct polarity.
To check the start cycle operation, take appropriate measures to prevent S2 from starting (if
configured as a generator by disconnecting the start output) and press the MANUAL
mode
button. Check to see if the start signal energises.
Set the modules internal clock/calendar to ensure correct operation of the scheduler and event
logging functions. For details of this procedure see section entitled Front Panel Configuration –
Editing the date and time.
If, despite repeated checking of the connections between the controller and the customer’s
system, satisfactory operation cannot be achieved, then the customer is requested to contact the
factory for further advice on:-